> A hardware upgrade of the core Arista 7508 switch will be performed on > Friday October 26th, starting at 0700 UTC (midnight PDT). The maintenance > window is 8 hours long. Purpose: > > - 2x supervisors will be upgraded > > - 6x fabric modules will be upgraded, resulting in a backplane change > from a 7508E (Arad) to a 7508R (Jericho) > > - 2x 12-port 100G line cards will be replaced with 2x 36-port 100G line > cards > > This will be a major fabric disruption. About 155 of the SIX's current > 325 routers will be offline. >